Abstract background

Case: Safety Region Noord-Holland Noord (3)

How did the Safety Region Noord-Holland Noord get everyone on board to organize things differently? Part 3 covers the Act phase of the PDCA cycle and the start of a completely new one: from call-to-balloon to call-to-needle. The result: 20 minutes gained on a trajectory of 120 minutes.

Key takeaways

  • The whole call-to-balloon trajectory was reduced from 120 to 100 minutes on average: 20 minutes that can save lives.
  • The Act phase is the nursery of new plans: here the decision is taken to adjust standards, KPIs or execution.
  • Re-engineering moves tasks to where they save most time in the chain, even if that makes the work of one link heavier.
  • The approach was extended to stroke care (call-to-needle), where four lessons together save about 18 minutes.
  • Nobody plays the boss: “Yes, but I am the doctor” is no basis for a learning environment.

The Act phase: it really has to change

Martin Smeekes saw ever more sharply where gains could be made and how essential it was to keep looking at the total chain across all separate parties. This part discusses the last phase of one run of the PDCA cycle and the start of a new one (see part 1 and part 2). First the question is which scenarios exist, who may decide on a new scenario and who gets the mandate to enter a new Plan phase.

The yield of the Act phase is that people see that things really have to change and decide to start a process to follow a different scenario. Updating your plan is not the same as actually adjusting it; then you are already in the next Plan phase. In the Act phase you do take the decision to adjust your standards, KPIs or execution. Every next step described below contains at least one whole new PDCA cycle. The Act phase is the nursery of all those new plans.

The new scenario

Before the call-to-balloon programme it was customary for ambulances to arrive at the emergency department, even when the ECG had already shown that angioplasty was needed. The data showed that via the emergency department the patient made extra movements and often had to wait twice, and even longer at weekends. So the route was changed: when it is already known that angioplasty is needed, the ambulance goes straight to the treatment room. That gains three minutes on average.

The same applies to alerting the angioplasty team in the evening and at night. As soon as the ECG that the ambulance crew sends to the hospital shows that angioplasty is necessary, the team is called up automatically. It is no longer mobilized only after the patient arrives; its mobilization runs in parallel. The accordion works.

Re-engineering: shift tasks elsewhere in the chain

Once in the hospital, the ambulance crew used to put the patient on a stretcher at most. Now they go along into the cath lab and transfer the patient from the ambulance stretcher directly onto the treatment table. That saves one extra transfer, which carried risk, was unpleasant for the patient and cost time. It does mean that some links in the chain get a heavier job: in the ambulance the patient is already prepared further for the next step. In fact you increase the crew’s workload. But in the larger puzzle of gaining maximum speed, such shifts are experienced as entirely logical.

The total result: time is muscle

No less than 20 minutes were gained on a trajectory that originally took 120 minutes: the whole call-to-balloon trajectory was reduced to 100 minutes on average.

This time is directly related to a better outcome for the patient. It is often the difference between a serious and a limited impairment, or no residual damage at all. Not for nothing is the adage among cardiologists “time is muscle”: the more time passes, the more permanent damage to the heart. And this was achieved in a region characterized by dunes, greenhouses and polders. Despite longer ambulance response times, heart attack patients are helped sooner and better. There are regions with far more favourable geography where the average of 100 minutes is not achieved.

Time for a completely new PDCA

After this success, the need arose to extend what had been learned. The new improvement question became: what can be improved before the call comes in that someone is having a heart attack? With that the plan shifts from call-to-balloon to symptom-to-balloon. A first form of scaling up took place when the Dutch National Health Care Institute used the experiences in its report “Spoed moet goed” (2015), which describes the blueprint for a national roll-out.

Scaling up to stroke: call-to-needle

A second form of scaling up was applying the principles to other medical incidents, starting with people who suffer a stroke. Like a heart attack, a stroke has critical time paths: all time gained is crucial to prevent residual damage. The danger to life decreases from the moment the patient is given a clot-dissolving drug safely and under control. So it is about the time between the first call to 112 and the administration of this drug: call-to-needle was born.

Cross-sectional learning with chain partners

These improvements did not arise from a plan thought out on paper, but on the shop floor. All professionals in the chain visited each other, collected and analyzed data at the workplace and looked for improvements together. Neurologists and nurses heard calls as they really come in at the control room, for the first time. A world opened up, and professionals gained more understanding for each other: distilling the right information from a confused call with a panicking partner is difficult and clever. Everything was aimed at the question of who can best perform which actions, in the interest of speed: agile, in other words.

Nobody plays the boss

The laboratory technician, the neurologist, the emergency physician, the neurological nurse and the ambulance nurse all sit around one large table. They may all say something, also about the process of the other participants. “Yes, but I am the doctor” is no basis for a learning environment. It is the responsibility of all chain partners together to organize their cooperation so that treatment proceeds as quickly as possible, without sacrificing safety or reliability.

Four lessons from the stroke chain

  1. Have the partner at home put the medication ready. Ambulance staff suggested that the control room ask the partner to collect all the patient’s medicines. With everything together, the crew sees at once whether a patient takes an anticoagulant and that the clotting value must be measured. Time gained: 2 minutes on average.
  2. Insert the second drip in the ambulance. Normally only one drip is inserted in the ambulance, while the hospital needs a second one for this treatment. Ambulance staff are very skilled at this, so they now do it as standard. Time gained: 1.5 minutes on average.
  3. Measure the clotting value in the ambulance. On arrival it is then already known whether the blood is thin, so the right medication can be given sooner. Time gained: 2.5 minutes on average.
  4. The neurologist comes to the CT scan. Neurology departments are traditionally located far from the emergency department. The patient no longer goes first to the CT scan and then to neurology; the neurologist comes to the scan. Time gained: 12 minutes on average.

Time gained per lesson in the stroke chain

Small shifts in the chain add up to about 18 minutes.

What changes

Average time gained

Medication

Partner puts medicines ready

2 minutes

Second drip

Inserted in the ambulance

1.5 minutes

Clotting value

Measured in the ambulance

2.5 minutes

CT scan

Neurologist comes to the scan

12 minutes

The call for culture change: from cardiology to neurology

The datacratic PDCA cycle fits the culture of cardiology, which internationally is geared to speed in its DNA. The transfer to neurology is a small step for the safety region, but a giant leap for the discipline. In neurology, looking at speed is fairly new. It was traditionally a department for diseases that were often hard to treat, where time never really played a role; that is also why it usually lay furthest from the emergency department. With the introduction of new clot-dissolving drugs, speed is becoming a factor of significance here too.

At international congresses where representatives of the region speak about call-to-needle, neurologists from Norway, the United States, Australia and England are often amazed and say they should do this too. Thinking in terms of speed and the accompanying improvement culture, let alone datacratic working, is often still absent. That is a great opportunity.

How Diamond Decisions keeps the PDCA cycle turning

Diamond Decisions helps organizations not to stop after the first improvement. In business modeling we define the next improvement question, with data analytics we measure the effect of every change, and we bring decision makers and chain partners around one table.

Conclusion

The case shows what a data-driven PDCA cycle yields when it keeps turning: twenty minutes on the heart attack chain, about eighteen on the stroke chain, and an improvement culture that spreads from one discipline to the next. The decisive factors were not technology, but measuring the whole chain, sharing the facts and deciding together.

Talk to the author

Daan van BeekDaan van Beek
Diamond Decisions

Discuss your question with Daan

Tell us which challenge in this story you recognize. In a no-obligation conversation we translate the lessons to your organization.

Schedule an introduction →

Diamond Decisions

Our approach in 4 steps

From inspiration and business model to data analysis and better decisions: this is how we approach it for you too.

Explore our approach →

Frequently asked questions

01

How much time was gained on the call-to-balloon trajectory?

Twenty minutes: the trajectory from the emergency call to the angioplasty was reduced from 120 to 100 minutes on average, through direct dispatch, an earlier ECG, a direct route to the cath lab and parallel mobilization of the team.

02

What is the difference between call-to-balloon and call-to-needle?

Call-to-balloon is the time from the emergency call to angioplasty for a heart attack. Call-to-needle is the time from the emergency call to the administration of a clot-dissolving drug for a stroke. Both measure the whole chain.

03

What happens in the Act phase of the PDCA cycle?

In the Act phase people conclude from the Check that things must change and decide to adjust standards, KPIs or execution. The actual adjustment of the plan belongs to the next Plan phase.

04

What does re-engineering mean for a smaller organization?

Moving a task to the place in the chain where it saves most time overall, even if it makes one step heavier. In an SME: have sales check data that otherwise delays planning, or have the warehouse prepare what production needs.

Further reading

Sources

  • Zorginstituut Nederland, Spoed moet goed (2015)

About the author

Daan van Beek

Daan van Beek

Daan co-founded Diamond Decisions and leads its further growth. He helps organisations translate strategy into day-to-day practice through a human-centred approach to data-driven working, and learns something new in every sector he works in.

About Diamond Decisions

Diamond Decisions helps organizations become better by enabling better decisions. We don’t start with data, dashboards or AI, but with the decision that needs to improve, and work back from there to KPIs, data and technology. We do that in four steps: inspiration and alignment, business modeling, analytics and data platform and data-driven decision makers. That way BI and AI don’t remain an IT project, but deliver value every day.

Schrijf je in voor de Masterclass